Rocky Mountain Regional VA Medical Center — Cost, Design, and Recovery Intelligence

A Guided Proof demonstration of how design growth, budget warnings, delivery-strategy changes, schedule slippage, and responsibility can be joined before exposure compounds.

ProjectReplacement Denver VA Medical Center
LocationAurora, Colorado
OwnerU.S. Department of Veterans Affairs
Recovery managerU.S. Army Corps of Engineers
Primary recordVA Office of Inspector General Report 15-03706-330
Initial estimate noted by OIG$328 million in 2004
2016 estimate noted by OIG$1.675 billion, plus activation cost
Known outcomeVeteran services began in 2018
Controlled Version 1.0
Validation Question

Could CFIG have joined the repeated cost, design, schedule, staffing, and contract warnings before they became one large recovery problem?

Yes. The federal audit record shows repeated estimates above budget, incomplete design, complex features, a midstream delivery change, slow modifications, and weak oversight. Those facts support an executive stop, reforecast, simplify, or change-delivery gate.

Evidence posture: Direct federal audit support for planning and design failure, ignored cost warnings, delivery-method problems, schedule and modification controls, later recovery, and 2018 service start.
Portfolio purposeThis project demonstrates full-life-cycle megaproject warning integration. It shows how CFIG makes separate design, cost, contract, staffing, and schedule warnings visible as one executive decision condition.
Controlled Guided Proof EditionTF-CFIG-RMV-GP-004 · Version 1.0 · Human Authority: Carl Wilson · September 4, 2026
CFIG Quick Proof and Guided Tour

What CFIG Discovered + Its Significance = Tangible Options

Project Purpose and Scope

The Department of Veterans Affairs undertook a replacement medical center in Aurora, Colorado, to expand care and replace an aging facility for veterans in the region. The project passed through repeated changes in concept, design, cost, procurement, construction, recovery, and eventual opening. This portfolio examines how federal oversight records connect those decisions across the project’s full lifecycle.

Portfolio Highlights

This portfolio places particular attention on:

  • Phase 2 — Planning and Project Definition: Repeated changes in concept, scope, and cost targets.
  • Phase 3 — Design and Preconstruction: Design maturity, complexity, and constructability against the approved budget.
  • Phase 4 — Contract and Procurement: Delivery strategy, contract obligations, and the effect of changing approach during execution.
  • Phase 5 — Guaranteed Maximum Price and Cost Formation: Divergent estimates and the failure to reconcile design with the construction cost target; the record describes an estimated contract cost, not a verified guaranteed maximum price.
  • Phase 6 — Construction and Project Controls: Staffing, schedule, decisions, and progress against the unresolved design and cost position.
  • Phase 7 — Changes and Claims: Contract modifications, work interruption, dispute, settlement, and recovery management.

These phases show how warnings in separate records accumulated into a project-wide decision condition. The eight-phase guide connects each phase to a finding or source while stating what the reviewed records do and do not establish. CFIG’s analysis is retrospective; CFIG did not participate in the project.

Emphasized phases are shown in green and gold.

Evidence Reviewed

The 82-page VA Office of Inspector General review, Government Accountability Office updates, and VA’s facility history.

What CFIG Discovered

Cost warnings, incomplete design, complex scope, procurement changes, staffing, and slow decisions formed one escalating condition.

Significance

The connected condition affected capital cost, schedule, contract position, accountability, and when veterans could use the replacement center.

Decision Window

When contractor and independent estimates warned that the design exceeded the construction cost target, before later changes became harder to reverse.

CFIG Response

Assemble an early warning register, reconciled change and contingency reforecast, and named executive decision matrix for the authorized officials.

Consequences of Taking No Action

Continuing construction while design, cost, and decision gaps remained unresolved could intensify delay, disputes, and capital pressure.

Controlled statusApproved controlled redesign based on completed federal oversight and operating-outcome records.
Professional boundaryThis demonstration uses public audit, accountability, and owner history records. It does not reperform design, cost, legal, or healthcare-facility reviews.
START THE GUIDED PROOF TOUR EXPLORE ALL EIGHT PHASES

Interactive Proof Chain

Select any stage for its supporting detail, or follow the chain from 1 through 9.

GUIDED PROOF TOUR — STEP 1 OF 9YOU ARE HERE: What CFIG Reviewed

What CFIG Reviewed

CFIG began with the named public records and stated the review limit before drawing a conclusion.

Reviewed core

The 82-page Veterans Affairs Office of Inspector General review, Government Accountability Office updates, the 2011 award notice, and the VA facility history.

Review boundary

The public oversight spine was reviewed. The full contract, design, change-order, claim, and confidential project corpus was not independently re-audited.

Source setVA OIG Report 15-03706-330; GAO-14-548T; GAO-18-329T; VA Eastern Colorado facility history
Review dateSeptember 4, 2026
Evidence postureDirect federal audit support for planning and design failure, ignored cost warnings, delivery-method problems, schedule and modification controls, later recovery, and 2018 service start.
Full recordSource Register and Coverage Ledger below the tour.
GUIDED PROOF TOUR — STEP 2 OF 9YOU ARE HERE: What CFIG Discovered

What CFIG Discovered

CFIG connected separate facts into one clear decision condition.

1 · Budget warningSeveral estimates showed the design was above the approved construction amount.
2 · Design maturityConstruction moved while design and constructability issues were still changing.
3 · Delivery shiftThe acquisition strategy changed from design-bid-build to an integrated form midstream.
4 · Control gapStaffing, decision speed, estimate reconciliation, and change tracking did not work as one control system.

WHAT CFIG DISCOVERED, CONNECTED, OR WOULD ENABLE

CFIG connected repeated estimates above budget, design complexity, incomplete construction documents, delivery-method change, slow decisions, and unclear accountability into one escalating cost-and-schedule condition.

GUIDED PROOF TOUR — STEP 3 OF 9YOU ARE HERE: Verify the Exact Source

Verify the Exact Source

The exact source is placed here so the reader does not need to hunt through the full record.

Exact evidence card

WHAT THE SOURCE SAYS

VA Office of Inspector General Report 15-03706-330 — Review of the Replacement of the Denver Medical Center

Physical PDF page 24, printed report page 17, “VA Officials Disregarded Warnings That Costs Trended Above the ECCA.”

“Senior VA officials disregarded numerous project cost estimates and information from various sources that VA could not build the Denver project.”

PLAIN-LANGUAGE TRANSLATION

Several estimates said the plan cost too much, but leaders kept the same path.

What CFIG detected or connectedThe budget warning was repeated, came from more than one source, and needed an executive stop-and-reforecast decision.
Lifecycle phasePlanning and Project Definition; Design and Preconstruction; Guaranteed Maximum Price, Cost Formation, and Purchasing.
Project effectCapital cost, schedule, scope, contract position, public accountability, and time to serve veterans.
Evidence statusDirectly supported by the federal Inspector General report.
OPEN THE ORIGINAL DOCUMENT
GUIDED PROOF TOUR — STEP 4 OF 9YOU ARE HERE: Significance

Significance

The condition matters because it can move through cost, time, responsibility, safety, or project outcome.

Cost effect

The federal record shows the estimate grew from $328 million in 2004 to $1.675 billion in the 2016 review.

Time effect

The completion estimate moved years beyond the original September 2013 target.

Contract effect

Incomplete design, delivery-strategy change, and slow modifications weakened control of price and responsibility.

Mission effect

Delay pushed back use of the replacement medical center for veterans and staff.

Lifecycle movementNeed → Scope and site → Design → Estimate → Contract strategy → Construction → Changes and dispute → Federal recovery and activation.
Primary benefitMakes compounding exposure visible early and supports accountable recovery decisions.
GUIDED PROOF TOUR — STEP 5 OF 9YOU ARE HERE: Decision Window

Decision Window

The useful time to act was before the next commitment made the problem harder or more costly to change.

Early windowWhen the project scope and $328 million estimate were first set in 2004.
Best action windowWhen contractor and independent estimates showed the design could not be built within the $604 million construction amount.
Recovery windowBefore construction stopped and before the U.S. Army Corps of Engineers took over completion management.
Closeout windowBefore activation, patient transfer, and final cost and change records were closed.
GUIDED PROOF TOUR — STEP 6 OF 9YOU ARE HERE: Action CFIG Would Take

Action CFIG Would Take

CFIG would turn the evidence into three separate work products that a responsible person can use.

PRIMARY TANGIBLE OPTION 1 OF 3

Cost–Schedule–Design Early Warning Register

Usable output
One dated register joining each estimate, design maturity point, schedule impact, warning source, owner response, and decision due date.
Responsible user
VA executive leadership, construction management, project controls, designer, and oversight teams.
Decision enabled
Whether to hold, simplify, redesign, add funds, or change delivery before more work proceeds.
Expected result
Warnings become action gates instead of background reports.

Benefit: Earlier control of compounding cost and delay.

PRIMARY TANGIBLE OPTION 2 OF 3

Change and Contingency Reforecast

Usable output
A reconciled forecast showing base scope, design growth, pending changes, contingency use, schedule effect, confidence range, and funding gap.
Responsible user
Project controls, contracting officer, finance, executive sponsor, and recovery manager.
Decision enabled
What the real completion forecast is and which changes can still be avoided or sequenced.
Expected result
Leaders act from one current forecast.

Benefit: More credible funding and recovery choices.

PRIMARY TANGIBLE OPTION 3 OF 3

Executive Responsibility and Decision Matrix

Usable output
A named map of who recommends, reviews, approves, funds, signs, and escalates each design, cost, schedule, and contract decision.
Responsible user
VA leadership, contracting, designer, contractor, Army Corps, and oversight bodies.
Decision enabled
Who must decide each open issue and when authority transfers.
Expected result
No material warning sits between organizations without an owner.

Benefit: Faster decisions and a stronger accountability record.

Control rule: These are three separate usable outputs. Carl Wilson, as Human Authority, decides which output is released and how it is used.
GUIDED PROOF TOUR — STEP 7 OF 9YOU ARE HERE: Decision Makers and Actions Enabled

Decision Makers and Actions Enabled

Each output has a named user and a clear decision. Human Authority remains in control.

VA executive sponsorHold or reset the project when the estimate and design do not match.
Contracting officerControl contract terms, modifications, scope, and formal direction.
Designer and builderReconcile design maturity, constructability, price, and schedule.
Project controls and oversightMaintain the independent warning record and confirm closure.
Decision questionShould the project hold, simplify, redesign, reforecast, add funding, change delivery, or escalate to recovery management?
Decision recordA signed executive record that states the current design basis, reconciled estimate, schedule, risk, authority, and chosen path.
Human AuthorityCarl Wilson controls final use, release, and escalation.
GUIDED PROOF TOUR — STEP 8 OF 9YOU ARE HERE: Consequences of Taking No Action

Consequences of Taking No Action

If the condition is not controlled, the project can lose time, money, leverage, safety, or operating value.

Compounding cost

Work can continue while design and estimate gaps keep creating new changes.

Schedule loss

Late redesign can stop connected work and move activation years later.

Dispute and leverage loss

Unclear scope, direction, and decision timing can turn project problems into contract disputes.

Mission delay

Veterans and staff wait longer for a usable facility while public funding pressure grows.

GUIDED PROOF TOUR — STEP 9 OF 9YOU ARE HERE: Verify the Finding Against Source Records

Verify the Finding Against Source Records

The proof chain below connects the claim to the exact public record and states the evidence limit.

SourceVA Office of Inspector General Report 15-03706-330 — Review of the Replacement of the Denver Medical Center
Exact locationPhysical PDF page 24, printed report page 17, “VA Officials Disregarded Warnings That Costs Trended Above the ECCA.”
Condition foundCFIG connected repeated estimates above budget, design complexity, incomplete construction documents, delivery-method change, slow decisions, and unclear accountability into one escalating cost-and-schedule condition.
CFIG interventionFreeze scope and design maturity, reconcile independent estimates, reforecast cost and schedule, and assign named executive decision owners.
Three Tangible OptionsCost–Schedule–Design Early Warning Register; Change and Contingency Reforecast; Executive Responsibility and Decision Matrix
DecisionShould the project hold, simplify, redesign, reforecast, add funding, change delivery, or escalate to recovery management?
Expected resultMakes compounding exposure visible early and supports accountable recovery decisions.
Evidence statusDirect federal audit support for planning and design failure, ignored cost warnings, delivery-method problems, schedule and modification controls, later recovery, and 2018 service start.

Verification card

WHAT THE SOURCE SAYS

VA Office of Inspector General Report 15-03706-330 — Review of the Replacement of the Denver Medical Center

Physical PDF page 24, printed report page 17, “VA Officials Disregarded Warnings That Costs Trended Above the ECCA.”

“Senior VA officials disregarded numerous project cost estimates and information from various sources that VA could not build the Denver project.”

PLAIN-LANGUAGE TRANSLATION

Several estimates said the plan cost too much, but leaders kept the same path.

What CFIG detected or connectedThe budget warning was repeated, came from more than one source, and needed an executive stop-and-reforecast decision.
Lifecycle phasePlanning and Project Definition; Design and Preconstruction; Guaranteed Maximum Price, Cost Formation, and Purchasing.
Project effectCapital cost, schedule, scope, contract position, public accountability, and time to serve veterans.
Evidence statusDirectly supported by the federal Inspector General report.
OPEN THE ORIGINAL DOCUMENT
Boundary: This demonstration uses public audit, accountability, and owner history records. It does not reperform design, cost, legal, or healthcare-facility reviews.
Complete Portfolio Evidence and Lifecycle Record

Continue into the full supporting portfolio

The guided tour gives the short answer. The record below preserves the project purpose, source coverage, lifecycle analysis, three Tangible Options, limits, and Human Authority.

OPEN THE FIRST FULL-PORTFOLIO SECTION
Reader Guide

Why this project is in the CFIG demonstration set

Demonstration purposeThis project demonstrates full-life-cycle megaproject warning integration. It shows how CFIG makes separate design, cost, contract, staffing, and schedule warnings visible as one executive decision condition.

Primary CFIG capability

Integrated early warning, reforecasting, and responsibility control.

Decision sweet spot

When independent estimates first showed the design could not be built within the approved construction amount.

Client payoff

Makes compounding exposure visible early and supports accountable recovery decisions.

This is an independent historical demonstration built from public records. It does not claim CFIG worked on, advised, or was endorsed by the project.

Executive Summary

One condition. One decision path. Three usable outputs.

Cost warnings, incomplete design, complex scope, a changed delivery method, and weak decision controls were connected—not isolated.

ConditionCFIG connected repeated estimates above budget, design complexity, incomplete construction documents, delivery-method change, slow decisions, and unclear accountability into one escalating cost-and-schedule condition.
InterventionFreeze scope and design maturity, reconcile independent estimates, reforecast cost and schedule, and assign named executive decision owners.
BenefitMakes compounding exposure visible early and supports accountable recovery decisions.

Primary evidence spine

WHAT THE SOURCE SAYS

VA Office of Inspector General Report 15-03706-330 — Review of the Replacement of the Denver Medical Center

Physical PDF page 24, printed report page 17, “VA Officials Disregarded Warnings That Costs Trended Above the ECCA.”

“Senior VA officials disregarded numerous project cost estimates and information from various sources that VA could not build the Denver project.”

PLAIN-LANGUAGE TRANSLATION

Several estimates said the plan cost too much, but leaders kept the same path.

What CFIG detected or connectedThe budget warning was repeated, came from more than one source, and needed an executive stop-and-reforecast decision.
Lifecycle phasePlanning and Project Definition; Design and Preconstruction; Guaranteed Maximum Price, Cost Formation, and Purchasing.
Project effectCapital cost, schedule, scope, contract position, public accountability, and time to serve veterans.
Evidence statusDirectly supported by the federal Inspector General report.
OPEN THE ORIGINAL DOCUMENT
Source Register and Coverage Ledger

What was reviewed—and what remains outside the claim

The register names each public record used here. “Targeted” means the listed project sections were reviewed for this demonstration. It does not mean every linked attachment or all project files were reviewed.

IDOriginal document and exact areaCoverage usedStatusPublic source
S1VA OIG Report 15-03706-330
82-page federal review; Findings 1–4, chronology, design phases, and management response.
Targeted review of the complete report with exact reliance on Findings 1–4.VERIFIEDOpen original source
S2GAO-14-548T
Government Accountability Office update on Denver cost, schedule, and scope.
Key findings and cost history reviewed.VERIFIEDOpen original source
S3GAO-18-329T
Government Accountability Office follow-up on cost estimates, schedules, and change-order tracking.
Key findings and follow-up status reviewed.VERIFIEDOpen original source
S4VA Eastern Colorado facility history
Official owner history through construction pause, Army Corps recovery, and 2018 patient transfers.
Outcome timeline reviewed.SUPPORTINGOpen original source
Full Project Lifecycle · Evidence Boundaries

Explore the VA medical center across all eight phases

Federal oversight follows the project from early decisions through recovery and operation. Each phase links to the relevant evidence or findings, with limits where the source set is narrower.

Phase 1 · Supporting site evidence

Land / Site Acquisition

Evidence reviewed: The Inspector General describes changing site concepts and the VA purchase of roughly 30 acres in Aurora by October 2008. The reviewed sources are not a complete parcel or title audit.

Decision use and limit: Connect site and care-delivery decisions to scope and budget without claiming a full land-record review.

Phase 2 · Strong federal oversight evidence

Planning / Project Definition

Evidence reviewed: Changes to the concept, scope, design, budget, and completion dates across successive leadership decisions are documented in the Inspector General review.

Decision use and limit: Freeze the mission need, scope, funding ceiling, and executive decision owners before additional commitments.

Phase 3 · Strong federal oversight evidence

Design / Preconstruction

Evidence reviewed: The Inspector General describes design complexity and a failure to ensure the design could be built within the target construction cost.

Decision use and limit: Demand a design-to-budget reconciliation and a documented constructability decision.

Phase 4 · Strong federal oversight evidence

Contract / Procurement

Evidence reviewed: The Inspector General addresses contract provisions, acquisition strategy, and the effect of changing delivery methods and issuing incomplete construction documents.

Decision use and limit: Make scope maturity, contracting authority, price basis, and risk allocation visible at procurement gates.

Phase 5 · Strong cost evidence; no verified GMP

Guaranteed Maximum Price / Cost Formation

Evidence reviewed: The report documents divergent designer and contractor estimates, a construction cost target, unreconciled design, and subsequent cost growth. It does not establish a guaranteed maximum price for this project.

Decision use and limit: Keep a reconciled estimate, contingency, and change forecast with an owner and decision date.

Phase 6 · Strong federal oversight evidence

Construction / Project Controls

Evidence reviewed: The review identifies staffing and decision weaknesses, construction delays, and cost and design questions that continued during field work.

Decision use and limit: Join schedule, progress, design release, staffing, and unresolved decisions in one warning register.

Phase 7 · Strong dispute and recovery evidence

Changes / Claims / Disputes

Evidence reviewed: Federal records describe slow modifications, work interruption, dispute, new contract arrangements, and Army Corps support for completion.

Decision use and limit: Track each change or claim with cause, cost, schedule, authority, and documented resolution; do not promise a different historical outcome.

Phase 8 · Documented opening; limited warranty detail

Closeout / Warranty / Operations

Evidence reviewed: The federal review and GAO updates address recovery and activation, and VA history records the new center’s operation. This source set does not establish a complete warranty or final-account audit.

Decision use and limit: Preserve cost and decision lessons for the operating owner while separating activation from warranty verification.

Complete Portfolio Evidence and Lifecycle Record

The eight CFIG lifecycle phases

A phase may be evidence-supported, supporting, or requirements-only. No blank phase is presented as completed field proof.

PhaseCoverage statusProject evidenceCFIG use
1. Land and Site AcquisitionEVIDENCE-SUPPORTEDColocation and site history appear in federal chronology and owner records.Tie site and partnership choices to scope, cost, and delivery risk.
2. Planning and Project DefinitionEVIDENCE-SUPPORTEDChanging concept, scope, budget, and completion targets.Freeze mission need, scope, cost limit, and executive gate.
3. Design and PreconstructionEVIDENCE-SUPPORTEDOIG Finding 1 documents planning, design, complexity, and constructability problems.Require design-to-budget and independent constructability proof.
4. Contract and ProcurementEVIDENCE-SUPPORTEDOIG Findings 2–3 address inadequate plans and midstream acquisition-strategy change.Test delivery method, design maturity, authority, and risk allocation before award.
5. Guaranteed Maximum Price, Cost Formation, and PurchasingEVIDENCE-SUPPORTEDMultiple estimates, failed reconciliation, cost growth, and contingency pressure.Maintain one reconciled estimate and change forecast.
6. Construction and Project ControlsEVIDENCE-SUPPORTEDConstruction progress, schedule slippage, staffing, and decision-control findings.Join design release, field progress, cost, schedule, and decision due dates.
7. Changes, Claims, Disputes, and Commercial ResolutionEVIDENCE-SUPPORTEDSlow modifications, work pause, litigation, settlement funding, and management transfer.Build a cause, entitlement, cost, schedule, and settlement record.
8. Closeout, Warranty, Audit, and Final ResolutionEVIDENCE-SUPPORTEDFederal audit, Army Corps recovery, facility activation, and 2018 service start.Preserve final cost, decisions, lessons, and operating handoff.
Detailed Findings

Source language beside plain language

RMV-01Repeated cost warnings required an executive gateCOST / GOVERNANCE

WHAT THE SOURCE SAYS

VA OIG Report 15-03706-330

“Senior VA officials disregarded numerous project cost estimates and information from various sources”

Physical PDF page 24, printed report page 17.

Open original source

PLAIN-LANGUAGE TRANSLATION

More than one source warned that the design cost too much.

WHAT CFIG DISCOVERED, CONNECTED, OR WOULD ENABLE

Condition Found

The budget gap was a repeated control signal, not one uncertain estimate.

Significance

Continuing without a reset lets design and construction lock in more cost.

Lifecycle Effect

Design → Estimate → Executive gate → Contract and construction.

Decision Window

At the first reconciled estimate above the approved amount.

CFIG Intervention

Use the Cost–Schedule–Design Early Warning Register.

Responsible User

Executive sponsor, project controls, finance, and contracting.

Consequences of Taking No Action

The project can keep spending against a budget it cannot meet.

Expected Benefit

Leaders see the point where hold or redesign is cheaper than recovery.

Evidence status: Direct federal audit support.
RMV-02Construction moved without a stable design-to-budget basisDESIGN / REFORECAST

WHAT THE SOURCE SAYS

VA OIG Report 15-03706-330

“VA Initiated Construction Phase Without Adequate Design Plans”

Physical PDF page 32, printed report page 25, Finding 2 heading.

Open original source

PLAIN-LANGUAGE TRANSLATION

Building started before the plans were ready enough.

WHAT CFIG DISCOVERED, CONNECTED, OR WOULD ENABLE

Condition Found

Design maturity, price, sequence, and contingency were not locked together.

Significance

Late plan changes create rework, delay, and hard-to-price impacts.

Lifecycle Effect

Incomplete plans → Field release → Change → Delay and cost growth.

Decision Window

Before each construction package was released.

CFIG Intervention

Use the Change and Contingency Reforecast.

Responsible User

Designer, builder, project controls, contracting officer, and sponsor.

Consequences of Taking No Action

The forecast becomes less reliable as connected work proceeds.

Expected Benefit

A current forecast makes recovery choices visible before funds are committed.

Evidence status: Direct federal audit support.
RMV-03A midstream delivery change needed clear authority and skillsCONTRACT / RESPONSIBILITY

WHAT THE SOURCE SAYS

VA OIG Report 15-03706-330

“VA’s decision to change its acquisition strategy from a Design Bid-Build contract to an Integrated-Design and Construct contract mid-stream”

Physical PDF page 37, printed report page 30, Finding 3.

Open original source

PLAIN-LANGUAGE TRANSLATION

The owner changed how the project would be delivered after work had already begun.

WHAT CFIG DISCOVERED, CONNECTED, OR WOULD ENABLE

Condition Found

The new delivery method changed duties, risk, and needed skills.

Significance

A new contract method cannot fix design and cost problems unless authority and controls change too.

Lifecycle Effect

Delivery strategy → Roles → Direction → Changes → Dispute and recovery.

Decision Window

Before the acquisition strategy changed and before related agreements were signed.

CFIG Intervention

Use the Executive Responsibility and Decision Matrix.

Responsible User

Executive leadership, acquisition, contracting, design, and construction teams.

Consequences of Taking No Action

Decisions can fall between organizations and make delay harder to resolve.

Expected Benefit

Each material decision has one owner, one due date, and one record.

Evidence status: Direct federal audit support.
Tangible Options

Exactly three primary outputs

Each option is a usable work product. It names the user, the decision, and the payoff.

No.Tangible OptionUsable outputUserDecision enabledBenefit
1Cost–Schedule–Design Early Warning RegisterOne dated register joining each estimate, design maturity point, schedule impact, warning source, owner response, and decision due date.VA executive leadership, construction management, project controls, designer, and oversight teams.Whether to hold, simplify, redesign, add funds, or change delivery before more work proceeds.Earlier control of compounding cost and delay.
2Change and Contingency ReforecastA reconciled forecast showing base scope, design growth, pending changes, contingency use, schedule effect, confidence range, and funding gap.Project controls, contracting officer, finance, executive sponsor, and recovery manager.What the real completion forecast is and which changes can still be avoided or sequenced.More credible funding and recovery choices.
3Executive Responsibility and Decision MatrixA named map of who recommends, reviews, approves, funds, signs, and escalates each design, cost, schedule, and contract decision.VA leadership, contracting, designer, contractor, Army Corps, and oversight bodies.Who must decide each open issue and when authority transfers.Faster decisions and a stronger accountability record.
Completion Gate

Release controls and honest limits

PASS — Guided proofNine exact tour steps, three-way navigation, and direct evidence cards are present.
PASS — Tangible OptionsExactly three primary outputs name a user, decision, result, and benefit.
PASS — Source separationThe source words and the CFIG interpretation are shown in different boxes.
LIMIT — Evidence boundaryThis demonstration uses public audit, accountability, and owner history records. It does not reperform design, cost, legal, or healthcare-facility reviews.
LIMIT — Professional roleCFIG organizes records and decision intelligence. It does not replace licensed design, legal, safety, environmental, accounting, or regulatory professionals.
HUMAN AUTHORITYCarl Wilson controls approval, release, reliance, and any later use of this demonstration.
No guarantee: Tangible Options describe defensible decision support. They do not promise a project result or claim that CFIG performed work on the historical project.

RETURN TO THE 13-PROJECT COLLECTION

Return to CFIG Site